PROJECT INFORMATION

Completed in 2011, the Addition and Renovation to Western Branch High School included three new building additions totaling more than 70,000 square feet and over 250,000 square feet of renovations to the existing building. The project included a complex phasing plan to allow the building to remain occupied throughout construction. All construction activities had to be coordinated around the school’s operations. The final contract value for this project was nearly $16 million.